Monday, December 13, 2010

Hair Highlights Of 2010



Thursday 16 December

Great Expectations:


Wednesday 15 December

Today's stuff:
- the first steps is ready
- the tiles have been delivered
- the brick company came and made the Abschweizungen


Monday 13 December

This week begins not good:
- From the site electricity works only 1 circle
- The heater does not work
- The clinker company is once again not

On the topic of site electricity turned up we had today, but most trouble. The electric company can know at a not too pleasant conversation with the boss that if the Baustromkabel back on the street is that he is off us. Although we have made a reasonable construction of the road (as required at the beginning of the company!) He refused to help. The cable would necessarily have high above the street. The result of almost 3 hours of work can be seen, however:

After we had finished, the electric company as quickly and with remark "It really works." We were then easier for a half hour and again around 100 € to work again properly in the situation. Get the advantage that finally worked the heating!

We were of course not there. We wanted to build stairs today. Even so we started. This picture shows the beginning (we have already come even further) from the stairs from the EC to the DG:

Ergebnisse des Tages:
- 8°C Temperatursteigung
- 3 Treppenstufen

Morgen machen wir weiter!