Sunday, October 24, 2010

Black Blotvches On Lcd

construction Week 43 2010

30th October own performance Steichen exterior
Today we had to withdraw support to our external facade. The wood has a lot of structure, it has taken a long time. But the result speaks for itself. The color is almost the color of the window and is much more modern. We are curious how it will look with the roof tiles and bricks.


26th October 18.00 clock are already prepared some installations.
particular has done much in the attic. The Velux Venster was set;

The first insulation was laid in the ground, and fastened planking.

has also changed outside stuff. The dormer was insulated and made the pages. At the front pages was the Zierbeplankung attached and suspended the suspension of the rain gutter:


28th October 17.00 clock
one days on the job site was not directly equal a few increments means not noticed. It's crazy how quickly are changes. Today, all sides are level on the top floor and already is some proof.
The electrician from ELKU have given gas, the complete wiring is pulled across the house and installed as far as possible. It still lacks the earthed sockets and switches, because of course we have again what you want outside the standard range.


25th October 08.00 clock electrical, plumbing and installation work
Today was the first time really something going on the site. A total of eight people were busy building our house. Were
At 8.00 clock in the morning the chief engineer, the plumbing company and we Müller on the site. After we have spoken have carried the theme, the project supervisor was adopted and the Frank Miller got down to work. Today we started with the piping in the basement and in the guest bathroom.

After we had just finished talks with the supervisor and the plumbing, an order for electric cars were driven up to deliver installation. Less than 2 minutes later were also of the electricians ELKU from Berlin at the door. Even with whom we have spoken the issues. When I came back in the evening at the construction site a lot has happened. Were everywhere down the cables were holes drilled in the walls for electrical installations and pipes were laid in shower room and cellar.