If it's running, then it is ... unfortunately this week is not this saying true.
Nevertheless, some moods:
Wednesday 01 December: Site Talk with our construction manager.
The word must be done at home Danhaus not take too seriously, we must now determine. All that is not going well, or is not seen simply as "Danhaus task:
- It started with the site power, which costs about 300 € per month. Through the planning of the site electricity Danhaus 4 months is needed. = 1200 € + connection costs for the E. ON site electricity.
- The developer must take care of the disposal of all waste that is created on the site. Any mixed waste were mixed together in the container (eg, wood, Styrofoam, plaster waste) which provides for unnecessarily high cost. The invoice in the amount of nearly 500 € be made by the client, even apart from the approximately 30 wooden pallets that are still on the roadside. Sorting out of wood: 2 people for 3 hours.
Van 101 119 |
Van 101 127 |
Van 101 127 |
Van 101 127 |
Van 101 112 |
- The mason was planned before last week. Today, the brick company has reported more often to learn directly from owner. The bricks are (now 2 weeks after the deadline) is not ordered, and he hopes for good weather on a date next week. This creates yet a cold bridge to the basement, the result is that hang large drops on the freshly painted ceiling!
- If we were not accidentally been on the job site, our mist removal would have been poured with the floor. Has about 1.5 hours required by the client.
Van 101 116 |
total there are at least 12 hours for the company Danhaus been worked ... of course, and of course without compensation. This site electricity bills for scrap and the amount of 2000 €. Thanks for the honest information in advance ...
Danhaus here is his name as a premium manufacturer "is not just. Of manufactured home you can not talk in the fall and now we understand why the 100% Danhaus Payment on completion no longer offered. The firm must have probably been waiting a long time for the money of the customers ....
Tuesday 30 November
Due to the weather some trades are not started:
- is for the walls of the outer wall, unfortunately too cold. We hope for improvement (> 2 ° C) for next week.
- the heating company is still not there. The commissioning of the heating should also take place this week.
- The appointment with the painter has not occurred for unknown reasons. But we hope to short-term information and start filling.