Wednesday 01 December: Site Talk with our construction manager.
The word must be done at home Danhaus not take too seriously, we must now determine. All that is not going well, or is not seen simply as "Danhaus task:
- It started with the site power, which costs about 300 € per month. Through the planning of the site electricity Danhaus 4 months is needed. = 1200 € + connection costs for the E. ON site electricity.
- The developer must take care of the disposal of all waste that is created on the site. Any mixed waste were mixed together in the container (eg, wood, Styrofoam, plaster waste) which provides for unnecessarily high cost. The invoice in the amount of nearly 500 € be made by the client, even apart from the approximately 30 wooden pallets that are still on the roadside. Sorting out of wood: 2 people for 3 hours.
Van 101 119
- The floor-level shower in the bathroom is not at ground level, but a huge hole to fill what the tiler afdichten with Styrofoam, and concrete ... Only the tile, in which case we, know how it would look like? The channel is positioned by the plumbing company, then look for Danhaus known as the shower is. The polystyrene layer is not aware of the shower with isolated, the floor layers the shower not to be related to height. It is incomprehensible to the client.
Van 101 127
- It is announced by Danhaus that stroked Fermacell, or can be plastered (smooth surface). Either the sellers have never been to a construction site, or the buyer to lie deliberately. Gaps between the plates of up to one centimeter are not uncommon, and the corners must be provided at least of steel corners or mesh. All walls and ceilings must be filled. Cost to the owner about 1000 €. Thanks Danhaus ...
Van 101 127
- All around the staircase still looks a steel profile from the ceiling. We opted for a different reason EXPIRES stairs and in the fall of the completion of the staircase. Whether the assembly group is working again for the rest of it is doubtful whether the stairway is then processed with Fermacell is even more unlikely. We are waiting for an appointment ...
Van 101 127
Van 101 112
- The scaffolders scaffolding has to be drilled in the Holzfasade. The holes may be filled by the client. The holes are hard to reach without scaffolding. Estimated 2 hours for filling and painting in the fall when winter conditions.
- The mason was planned before last week. Today, the brick company has reported more often to learn directly from owner. The bricks are (now 2 weeks after the deadline) is not ordered, and he hopes for good weather on a date next week. This creates yet a cold bridge to the basement, the result is that hang large drops on the freshly painted ceiling!
- If we were not accidentally been on the job site, our mist removal would have been poured with the floor. Has about 1.5 hours required by the client.
Van 101 116

total there are at least 12 hours for the company Danhaus been worked ... of course, and of course without compensation. This site electricity bills for scrap and the amount of 2000 €. Thanks for the honest information in advance ...

Danhaus here is his name as a premium manufacturer "is not just. Of manufactured home you can not talk in the fall and now we understand why the 100% Danhaus Payment on completion no longer offered. The firm must have probably been waiting a long time for the money of the customers ....

Tuesday 30 November
Due to the weather some trades are not started:
- is for the walls of the outer wall, unfortunately too cold. We hope for improvement (> 2 ° C) for next week.
- the heating company is still not there. The commissioning of the heating should also take place this week.
- The appointment with the painter has not occurred for unknown reasons. But we hope to short-term information and start filling.