construction Week 51 2010 Week 50 2010
Monday 22 December
Today was quite a relief for us, the electrician from ELKU our electrical installation completed. Yesterday, the EO.N was already installed and the house connection. This meant a final relief from Baustomkasten electric Schmid from Manching. The cost that we paid for the Baustromkasten were enormous, although we still need power only ... The cost shall be Bauherren nicht bekannt. Zukuenftige Bauherren können wir nur empfehlen vorab bei der Baufirma zu informieren ueber die Zahlung der Kosten fuer die Miete. Die Firma Elektro Schmid berechnet zusätzlich Installationskosten, Kosten fuer Reparature und informiert den Bauherr zu wenig ueber Gefahre und notwendige Schuetz.
Inzwischen legen wir Fliesen im Badezimmer und machen alles mögliche um sicherzustellen, dass die Firmen weitermachen können.
Auch hat die Firma Acalor uns heute unterstützt bei unserem Wärmeproblem. Bis jetzt wird die Fußbodenheizung noch nicht wirklich warm. Durch den Ausfall des Baustroms während 4 Tage ist der Verdampfer anscheinend zu sehr vereist gewesen uns hat dafür gesorgt, dass das normale Enteisungsprogramm not enough. Today I made a telephone support a change in the program after the plant is about 1 hour run in Enteisungsprogramm. We hope for a rapid increase in temperature.
Monday 20 December
With a positive thought we start week. The week is predicted Tauwettet, which means that the builders could start and could lay the civil contractors, the pipes to the cistern. Let's hope ... would be a nice Christmas present.
Otherwise, we have yet some offers on the drywall (filling & painting) to obtain, since we are not satisfied with the range are. Today 2 of dry construction companies in the building were to assess the work. One of them is responsible for it.
The electrician from ELKU came. Expected tomorrow, the drama ended site electricity and we depend on "normal" network. Three days they will need and then the electrical work done.
Monday, December 20, 2010
Monday, December 13, 2010
Hair Highlights Of 2010
Thursday 16 December
Great Expectations:
Wednesday 15 December
Today's stuff:
- the first steps is ready
- the tiles have been delivered
- the brick company came and made the Abschweizungen
Monday 13 December
This week begins not good:
- From the site electricity works only 1 circle
- The heater does not work
- The clinker company is once again not
On the topic of site electricity turned up we had today, but most trouble. The electric company can know at a not too pleasant conversation with the boss that if the Baustromkabel back on the street is that he is off us. Although we have made a reasonable construction of the road (as required at the beginning of the company!) He refused to help. The cable would necessarily have high above the street. The result of almost 3 hours of work can be seen, however:
|
We were of course not there. We wanted to build stairs today. Even so we started. This picture shows the beginning (we have already come even further) from the stairs from the EC to the DG:
Ergebnisse des Tages:
- 8°C Temperatursteigung
- 3 Treppenstufen
Morgen machen wir weiter!
Thursday, December 9, 2010
Marriage Invite Tamil
Monday, December 6, 2010
Sibutramina Translate To English
house construction house construction house construction
Donnerstag 09. Dezember
Heute ist Acalor auf der Baustelle. Die Heizung ist installiert worden uns wurde gerade befüllt. Die Heizung ist in Betrieb genommen und mich erklärt worden. Viel einfacher geht es nicht.
Ab jetzt wird die Heizung das Estrichaufheizprogramm durchlaufen. Dieses Programm erhöht die Temperatur mit ca. 2°C/Tag bis 30°C Raumtemperatur erreicht wird.
Unfortunately, the Maurer
were still not there.
Tuesday 07 December
When we came in today to the site, the bricks were already there. Now we hope that the company supported the clinker Goellner soon as possible.
came in the late afternoon, two of Carpenters, which controlled by Danhaus, company. The upper stairwell was covered. The still closed stairwell from the basement to the EC is the next event (doors translated) made, here come the carpenter ran poorly at the moment. The train will then also went through the outer lining of the loggia, providing the missing materials have arrived ...
Danhaus has accepted our criticism und bemüht sich die Kundenzufriedenheit hoch zu halten. Lobenswert! Daran kann die Fa. Glatthaar sich ein Beispiel nehmen.
Montag 06. Dezember
Heute taut es. Das bedeutet neue Möglichkeiten für die Verklinkerung der Fassade. Direkt haben wir die Maurer angerufen, ob sie schon unterwegs sind. Leider nicht. Aber es wird versprochen, dass sie direkt nachdem sie auf der anderen Baustelle fertig sind, zu uns kommen. Hoffen wir die Temperatur bleibt lange genug oben.
Heute ist der Mörtel gekommen, morgen sollen die Klinker kommen. Der Mörteltransport über die Baustraße Richtung Haus war schon spannend genug. Mit einem Gabelstapler über die nicht geräumte Straße war für the driver an almost impossible task.
Also we were not bored, in the basement we painted a room and installed indirect lighting in the living room. Lunch was the laying of the carpet as to measure out the spaces. Appointment is for 3 January.
On Wednesday or Thursday to the heater to work, so at last it is warm in the house and the floor dries out properly.
Donnerstag 09. Dezember
Heute ist Acalor auf der Baustelle. Die Heizung ist installiert worden uns wurde gerade befüllt. Die Heizung ist in Betrieb genommen und mich erklärt worden. Viel einfacher geht es nicht.
Ab jetzt wird die Heizung das Estrichaufheizprogramm durchlaufen. Dieses Programm erhöht die Temperatur mit ca. 2°C/Tag bis 30°C Raumtemperatur erreicht wird.
Unfortunately, the Maurer
were still not there.
Tuesday 07 December
When we came in today to the site, the bricks were already there. Now we hope that the company supported the clinker Goellner soon as possible.
came in the late afternoon, two of Carpenters, which controlled by Danhaus, company. The upper stairwell was covered. The still closed stairwell from the basement to the EC is the next event (doors translated) made, here come the carpenter ran poorly at the moment. The train will then also went through the outer lining of the loggia, providing the missing materials have arrived ...
Danhaus has accepted our criticism und bemüht sich die Kundenzufriedenheit hoch zu halten. Lobenswert! Daran kann die Fa. Glatthaar sich ein Beispiel nehmen.
Montag 06. Dezember
Heute taut es. Das bedeutet neue Möglichkeiten für die Verklinkerung der Fassade. Direkt haben wir die Maurer angerufen, ob sie schon unterwegs sind. Leider nicht. Aber es wird versprochen, dass sie direkt nachdem sie auf der anderen Baustelle fertig sind, zu uns kommen. Hoffen wir die Temperatur bleibt lange genug oben.
Heute ist der Mörtel gekommen, morgen sollen die Klinker kommen. Der Mörteltransport über die Baustraße Richtung Haus war schon spannend genug. Mit einem Gabelstapler über die nicht geräumte Straße war für the driver an almost impossible task.
Also we were not bored, in the basement we painted a room and installed indirect lighting in the living room. Lunch was the laying of the carpet as to measure out the spaces. Appointment is for 3 January.
On Wednesday or Thursday to the heater to work, so at last it is warm in the house and the floor dries out properly.
Saturday, December 4, 2010
Tinkling Across My Shoulders Across My Neck
Tuesday, November 30, 2010
How Do I Reprogram My Redz Ion
2010 Week 49 Week 48 Week 47 2010 2010
If it's running, then it is ... unfortunately this week is not this saying true.
Nevertheless, some moods:
Wednesday 01 December: Site Talk with our construction manager.
The word must be done at home Danhaus not take too seriously, we must now determine. All that is not going well, or is not seen simply as "Danhaus task:
- It started with the site power, which costs about 300 € per month. Through the planning of the site electricity Danhaus 4 months is needed. = 1200 € + connection costs for the E. ON site electricity.
- The developer must take care of the disposal of all waste that is created on the site. Any mixed waste were mixed together in the container (eg, wood, Styrofoam, plaster waste) which provides for unnecessarily high cost. The invoice in the amount of nearly 500 € be made by the client, even apart from the approximately 30 wooden pallets that are still on the roadside. Sorting out of wood: 2 people for 3 hours.
- The floor-level shower in the bathroom is not at ground level, but a huge hole to fill what the tiler afdichten with Styrofoam, and concrete ... Only the tile, in which case we, know how it would look like? The channel is positioned by the plumbing company, then look for Danhaus known as the shower is. The polystyrene layer is not aware of the shower with isolated, the floor layers the shower not to be related to height. It is incomprehensible to the client.
- It is announced by Danhaus that stroked Fermacell, or can be plastered (smooth surface). Either the sellers have never been to a construction site, or the buyer to lie deliberately. Gaps between the plates of up to one centimeter are not uncommon, and the corners must be provided at least of steel corners or mesh. All walls and ceilings must be filled. Cost to the owner about 1000 €. Thanks Danhaus ...
- All around the staircase still looks a steel profile from the ceiling. We opted for a different reason EXPIRES stairs and in the fall of the completion of the staircase. Whether the assembly group is working again for the rest of it is doubtful whether the stairway is then processed with Fermacell is even more unlikely. We are waiting for an appointment ...
- The scaffolders scaffolding has to be drilled in the Holzfasade. The holes may be filled by the client. The holes are hard to reach without scaffolding. Estimated 2 hours for filling and painting in the fall when winter conditions.
- The mason was planned before last week. Today, the brick company has reported more often to learn directly from owner. The bricks are (now 2 weeks after the deadline) is not ordered, and he hopes for good weather on a date next week. This creates yet a cold bridge to the basement, the result is that hang large drops on the freshly painted ceiling!
- If we were not accidentally been on the job site, our mist removal would have been poured with the floor. Has about 1.5 hours required by the client.
total there are at least 12 hours for the company Danhaus been worked ... of course, and of course without compensation. This site electricity bills for scrap and the amount of 2000 €. Thanks for the honest information in advance ...
Danhaus here is his name as a premium manufacturer "is not just. Of manufactured home you can not talk in the fall and now we understand why the 100% Danhaus Payment on completion no longer offered. The firm must have probably been waiting a long time for the money of the customers ....
Tuesday 30 November
Due to the weather some trades are not started:
- is for the walls of the outer wall, unfortunately too cold. We hope for improvement (> 2 ° C) for next week.
- the heating company is still not there. The commissioning of the heating should also take place this week.
- The appointment with the painter has not occurred for unknown reasons. But we hope to short-term information and start filling.
If it's running, then it is ... unfortunately this week is not this saying true.
Nevertheless, some moods:
Wednesday 01 December: Site Talk with our construction manager.
The word must be done at home Danhaus not take too seriously, we must now determine. All that is not going well, or is not seen simply as "Danhaus task:
- It started with the site power, which costs about 300 € per month. Through the planning of the site electricity Danhaus 4 months is needed. = 1200 € + connection costs for the E. ON site electricity.
- The developer must take care of the disposal of all waste that is created on the site. Any mixed waste were mixed together in the container (eg, wood, Styrofoam, plaster waste) which provides for unnecessarily high cost. The invoice in the amount of nearly 500 € be made by the client, even apart from the approximately 30 wooden pallets that are still on the roadside. Sorting out of wood: 2 people for 3 hours.
Van 101 119 |
Van 101 127 |
Van 101 127 |
Van 101 127 |
Van 101 112 |
- The mason was planned before last week. Today, the brick company has reported more often to learn directly from owner. The bricks are (now 2 weeks after the deadline) is not ordered, and he hopes for good weather on a date next week. This creates yet a cold bridge to the basement, the result is that hang large drops on the freshly painted ceiling!
- If we were not accidentally been on the job site, our mist removal would have been poured with the floor. Has about 1.5 hours required by the client.
Van 101 116 |
total there are at least 12 hours for the company Danhaus been worked ... of course, and of course without compensation. This site electricity bills for scrap and the amount of 2000 €. Thanks for the honest information in advance ...
Danhaus here is his name as a premium manufacturer "is not just. Of manufactured home you can not talk in the fall and now we understand why the 100% Danhaus Payment on completion no longer offered. The firm must have probably been waiting a long time for the money of the customers ....
Tuesday 30 November
Due to the weather some trades are not started:
- is for the walls of the outer wall, unfortunately too cold. We hope for improvement (> 2 ° C) for next week.
- the heating company is still not there. The commissioning of the heating should also take place this week.
- The appointment with the painter has not occurred for unknown reasons. But we hope to short-term information and start filling.
Wednesday, November 24, 2010
What Does Kirkland Paper Towels Have In It
house construction house construction
Saturday 27 November
The screed ist schon so weit ausgehärtet, dass er begehbar ist. Das haben wir denn auch gemacht, um direkt die erste Feuchte aus dem Räume zu lassen.
Mittwoch 24. November
BETRETEN VERBOTEN: Der Estrich wurde gelegt. Unser Haus ist die nächsten Tag nicht begehbar. Am Samstag sollten wir aber wieder mit den Malerarbeiten weitermachen können.
Dienstag 23. November
Am Dienstag wurde die Dämmung und Dampfsperre gelegt. Im Keller ist der Bodenaufbau nur 7 cm hoch:
- Dampfsperre
- Dämmung ca. 3 cm
- Estrich ca 3,5 - 4,0 cm
Saturday 27 November
The screed ist schon so weit ausgehärtet, dass er begehbar ist. Das haben wir denn auch gemacht, um direkt die erste Feuchte aus dem Räume zu lassen.
Mittwoch 24. November
BETRETEN VERBOTEN: Der Estrich wurde gelegt. Unser Haus ist die nächsten Tag nicht begehbar. Am Samstag sollten wir aber wieder mit den Malerarbeiten weitermachen können.
Dienstag 23. November
Am Dienstag wurde die Dämmung und Dampfsperre gelegt. Im Keller ist der Bodenaufbau nur 7 cm hoch:
- Dampfsperre
- Dämmung ca. 3 cm
- Estrich ca 3,5 - 4,0 cm
Tuesday, November 16, 2010
Isight Camera Is Not Working With Oovoo
Week 46 2010
20. November 08.00 Uhr
Früh auf der Baustelle, da sich heute wieder Einiges ändern wird. Unser Tiefbauer war schon wieder vor 6 Uhr auf der Baustelle, damit er diese enorme Aufgabe meistern kann. Unser Grundstück wird heute, rundum das Haus, auf Höhe gebracht, damit am Montag die Außenwanddämmung und der Verblendmauer angefangen werden kann.
Auch wir haben uns um einige Sachen gekümmert. Das Holz was noch überall aufs Grundstück lag hatten wir gestern schon großenteils aussortiert, heute haben wir die letzte Stücke weggeräumt.
Auch haben wir die Zisterne noch mal abgedichtet und am Ende des Tages im Erdgeschoss die Deckenspots ausgemessen und gebohrt.
19. November 12.00 Uhr
Oops...eine ganz wichtige Info vergessen. Das Scaffolding was removed on Wednesday and so we first see the house in full glory.
17th November 18.00 clock
The heater is now on the program, the company Acalor was there with 2 teams. We have finally received the day before the tubes for the hood. Everything worked perfectly and the Bora pipes are laid.
16th November 18.00
clock was today laid the floor insulation. The amount is enormous. But here also seems to want the communication to be desired. Although we had already laid in the weekend a pipe for the Bora-hood (unfortunately still missing some parts, but now replenished wurden), haben die Monteure sich dafür entschieden die Rohre zu entfernen und anstelle von den Rohren Dämmung zu verlegen. Wäre ich heute Abend nicht da gewesen wäre morgen die Fußbodenheizung darüber gelegen und wäre unsere Bora-Lösung Geschichte.
Auf provisorische Weise habe ich die Styroporblöcke gesägt und das Rohr neu verlegt (mir haben die passenden Werkzeuge ja gefehlt). Leider ist die Verarbeitung jetzt weit Weg von optimal. Ich hoffe nicht, dass hier eine Kältebrücke entsteht.
20. November 08.00 Uhr
Früh auf der Baustelle, da sich heute wieder Einiges ändern wird. Unser Tiefbauer war schon wieder vor 6 Uhr auf der Baustelle, damit er diese enorme Aufgabe meistern kann. Unser Grundstück wird heute, rundum das Haus, auf Höhe gebracht, damit am Montag die Außenwanddämmung und der Verblendmauer angefangen werden kann.
Auch wir haben uns um einige Sachen gekümmert. Das Holz was noch überall aufs Grundstück lag hatten wir gestern schon großenteils aussortiert, heute haben wir die letzte Stücke weggeräumt.
Auch haben wir die Zisterne noch mal abgedichtet und am Ende des Tages im Erdgeschoss die Deckenspots ausgemessen und gebohrt.
19. November 12.00 Uhr
Oops...eine ganz wichtige Info vergessen. Das Scaffolding was removed on Wednesday and so we first see the house in full glory.
17th November 18.00 clock
The heater is now on the program, the company Acalor was there with 2 teams. We have finally received the day before the tubes for the hood. Everything worked perfectly and the Bora pipes are laid.
16th November 18.00
clock was today laid the floor insulation. The amount is enormous. But here also seems to want the communication to be desired. Although we had already laid in the weekend a pipe for the Bora-hood (unfortunately still missing some parts, but now replenished wurden), haben die Monteure sich dafür entschieden die Rohre zu entfernen und anstelle von den Rohren Dämmung zu verlegen. Wäre ich heute Abend nicht da gewesen wäre morgen die Fußbodenheizung darüber gelegen und wäre unsere Bora-Lösung Geschichte.
Auf provisorische Weise habe ich die Styroporblöcke gesägt und das Rohr neu verlegt (mir haben die passenden Werkzeuge ja gefehlt). Leider ist die Verarbeitung jetzt weit Weg von optimal. Ich hoffe nicht, dass hier eine Kältebrücke entsteht.
Sunday, November 14, 2010
Religious Get Well Inspiration
target search 2011, 2012
The 2009/2010 season with an early Ironman Malaysia in February and late October in Hawaii was very long. I have almost 13 months without a break after my Trainingsplan gelebt und erlebe jetzt, was es heißt, "ziellos" zu sein. Das ist ja nicht wirklich schlimm, aber für mich eine lange hinter mir geglaubte Herausforderung.
Mir fällt es jetzt unendlich schwer, irgendeiner sportlichen Betätigung nachzugehen, weil sie noch nicht auf ein Ziel hinführt. Für Sport "einfach so" reicht meine Motivation einfach nicht aus.
So freue ich mich über jeden Anruf von Freunden, die einen Lauf-/Schwimm- oder Radpartner suchen. So weit reicht mein Bewegungsdrang dann doch, dass ich das nicht ausschlage.
Gestern beim Schwimmtraining im USC, meinem Triathlonverein, sagte mir Sascha, dass er plane, am Rotterdam Marathon am 10. April kommenden Jahres teilnehmen to do. Another club to join his colleague had also expressed readiness against him already. A Marathon in 2011 would Fühjahr ideal for me as my inner voice whispers a long time that I must still run a fast marathon anyway. The only "solo" marathon that I ran itself, is already 7 years, was at a time when I compared to today focusses not so trained, and only limited experience in endurance sports had to show.
Today, other times as a goal at that time, after all, a 3:02 in Hamburg will be targeted. Based on the current performance and experience should, if all goes well, 2:50 a possible, provided perfect preparation and a fast track. Memories of the in 2003 physically extremely painful preparation have stifled another attack on my marathon personal best so far in the bud, but now the time seems to be ripe and fit to the appointment.
As IRONMAN climax 2011 I have registered in the past week at the IM-Florida, which took place on 5/11/2011. Michael and Daniela, just two in Florida in their respective age groups M45 and W25 imports swarmed the victory, so much of the event, that I booked myself. Since Florida a "qualifier" for the Hawaii Ironman in 2012, I like very well. In 2012, I would like to try that is a newcomer in the next step M50 to achieve a good placing in the age group and if the quality does not work, then I have another attempt in the first half of 2012th
with a marathon in April and an Ironman in November, the framework for my future active life is set. Now have to use only the plan that requires me again day after day, I have to train. Then finally it's over with the frigging and again plenty of time for me to remember the "cozy time" back.
The 2009/2010 season with an early Ironman Malaysia in February and late October in Hawaii was very long. I have almost 13 months without a break after my Trainingsplan gelebt und erlebe jetzt, was es heißt, "ziellos" zu sein. Das ist ja nicht wirklich schlimm, aber für mich eine lange hinter mir geglaubte Herausforderung.
Mir fällt es jetzt unendlich schwer, irgendeiner sportlichen Betätigung nachzugehen, weil sie noch nicht auf ein Ziel hinführt. Für Sport "einfach so" reicht meine Motivation einfach nicht aus.
So freue ich mich über jeden Anruf von Freunden, die einen Lauf-/Schwimm- oder Radpartner suchen. So weit reicht mein Bewegungsdrang dann doch, dass ich das nicht ausschlage.
Gestern beim Schwimmtraining im USC, meinem Triathlonverein, sagte mir Sascha, dass er plane, am Rotterdam Marathon am 10. April kommenden Jahres teilnehmen to do. Another club to join his colleague had also expressed readiness against him already. A Marathon in 2011 would Fühjahr ideal for me as my inner voice whispers a long time that I must still run a fast marathon anyway. The only "solo" marathon that I ran itself, is already 7 years, was at a time when I compared to today focusses not so trained, and only limited experience in endurance sports had to show.
Today, other times as a goal at that time, after all, a 3:02 in Hamburg will be targeted. Based on the current performance and experience should, if all goes well, 2:50 a possible, provided perfect preparation and a fast track. Memories of the in 2003 physically extremely painful preparation have stifled another attack on my marathon personal best so far in the bud, but now the time seems to be ripe and fit to the appointment.
As IRONMAN climax 2011 I have registered in the past week at the IM-Florida, which took place on 5/11/2011. Michael and Daniela, just two in Florida in their respective age groups M45 and W25 imports swarmed the victory, so much of the event, that I booked myself. Since Florida a "qualifier" for the Hawaii Ironman in 2012, I like very well. In 2012, I would like to try that is a newcomer in the next step M50 to achieve a good placing in the age group and if the quality does not work, then I have another attempt in the first half of 2012th
with a marathon in April and an Ironman in November, the framework for my future active life is set. Now have to use only the plan that requires me again day after day, I have to train. Then finally it's over with the frigging and again plenty of time for me to remember the "cozy time" back.
Saturday, November 13, 2010
How Long For Aquarium Silicone To Dry
Monday, November 8, 2010
When Does A Male Get A Genital Examination
construction Week 45 2010
13. & 14. November 10.00 Uhr
Es ist wieder Wochenende und das bedeutet Stress; im Wochenende wird in der Regel rund 10 Stunden geschafft. Dieses Wochenende haben wir uns noch mal um das Streichen des Holzes gekümmert. Am Sonntag dann auch noch um:
- verlegen der Verrohrung des Dunstabzuges richtung Keller
- verlegen von einem Wasserrohr richtung Garten
- verlegen von einer Elektrokabel für den Carport bzw. ein Gartenhäuschen für die Zukunft
- abdichten der Zisterne
- abdichten der Rohre für den zentralen Elektroanschluss und Telekomanschluß.
Und das alles haben wir weitgehendst geschafft!
Die nächsten Schritte für Woche 46:
- Legen der Fußbodendämmung
- Legen der Fußbodenheizung
- Abbau vom Gerüst
- Auffüllen vom Grundstück
12. November 17.00 Uhr
Die Zimmerleute von Scheddin haben es geschafft! Sie sind leider später als gehofft gegangen, trotzdem sind die Arbeiten soweit erledigt. Es war nicht nur ein Zeitproblem, sondern auch ein Materialproblem. Das Fermacell hat gerade nicht mehr gereicht und die Latten draußen für die Loggia (im Giebel) waren zu kurz. Sonst wurde das problematische Thema im Badezimmer SUPER gelöst. besser hätte das aus unserer Sicht nicht gemacht werden können.
Auch die Loggia wurde so weit wie möglich fertig gemacht. Zum ersten Mal konnten wir auf dem Balkon mit Geländer stehen.
11th November 18.00 clock
Today we were only in the evening on the site. The men of the company Scheddin were also fully occupied. Unfortunately, it turned out that our drawings (which were also applied for planning permission) and the detailed drawing for the craftsmen were different. There was thus a problem in the bathroom. The pretext behind the bathtub was made as a closed wall, although we did have a shelf level with the top edge of the tub, as mentioned in the drawings.
The wall of the basin was made today ready. The sanitary Müller was again on site and also have the electrical work fertig gemacht (um eine Fahrt der Elektriker von Berlin nach Langenbruck zu sparen).
Wir wollten eine horizontale 120 cm lange Vertiefung in der 140 cm langen Wand haben, was aber aus Statiksicht nicht möglich war, da dann einige vertikalen Querhölzern unterbrochen werden müssten.
Morgen wollen die Tischler fertig werden, aus dem Grund sind sie ziemlich im Stress; das Badezimmer muss noch fertiggestellt werden, die Loggia ist noch komplett offen und es fehlen noch einige Feinarbeiten. Mal sehen wie es morgen weiter geht...
Wir haben heute nur ein zwei Elektrokabel Richtung Garden and driveway down by the still-open positions in EON-wall penetration.
09th November 19.00 clock
are today delivered the tiles. At the time where I was on site about one-third of the roof was covered with roof tiles. We need to look at the times in daylight, but I think that is very beautiful. The contrast with our lighter Fasadenfarbe is of course directly visible.
was also closed down on the ground floor the ceiling. The ceiling is clad entirely with Fermacell. Now we can start the spots to drill. Otherwise, the people are very busy with the roof.
morning visit during daylight and the whole thing looks like.
08th November 17.45 clock
Today, the company Scheddin back. If they are there mostly good stuff going forward, it is now going on with the detail work, as a precision tool with (!!!). the Kettingsäge This week, the wood work is finished.
was today made the bathrooms downstairs, and the installation of bathroom walls and side table have been completed. We still had some questions about the upstairs bathroom, all has been answered.
I also have used directly the question time to look to the questions whether Zimmerman's people have time and inclination to make the drywall in the kitchen, which was answered with a yes in principle. Even today we have the first style element in our TV wall cut. The box should be provided with a light. But had the power cables are redefined, then the wall cavity would be ready.
was made above the dormer finished. Now see how much space we gain in the two rooms at the front of our house, even with only 5.40 m wide dormer (instead 7m)
Erreichnis And most important of today and the cellar door is set. Finally we can sleep peacefully again. For weeks, some items were unsupervised in our open basement, now we can finally finish the basement. Also, we have directly the final key to our Get home. The lock cylinder needs to be replaced at the end of the work again.
13. & 14. November 10.00 Uhr
Es ist wieder Wochenende und das bedeutet Stress; im Wochenende wird in der Regel rund 10 Stunden geschafft. Dieses Wochenende haben wir uns noch mal um das Streichen des Holzes gekümmert. Am Sonntag dann auch noch um:
- verlegen der Verrohrung des Dunstabzuges richtung Keller
- verlegen von einem Wasserrohr richtung Garten
- verlegen von einer Elektrokabel für den Carport bzw. ein Gartenhäuschen für die Zukunft
- abdichten der Zisterne
- abdichten der Rohre für den zentralen Elektroanschluss und Telekomanschluß.
Und das alles haben wir weitgehendst geschafft!
Die nächsten Schritte für Woche 46:
- Legen der Fußbodendämmung
- Legen der Fußbodenheizung
- Abbau vom Gerüst
- Auffüllen vom Grundstück
12. November 17.00 Uhr
Die Zimmerleute von Scheddin haben es geschafft! Sie sind leider später als gehofft gegangen, trotzdem sind die Arbeiten soweit erledigt. Es war nicht nur ein Zeitproblem, sondern auch ein Materialproblem. Das Fermacell hat gerade nicht mehr gereicht und die Latten draußen für die Loggia (im Giebel) waren zu kurz. Sonst wurde das problematische Thema im Badezimmer SUPER gelöst. besser hätte das aus unserer Sicht nicht gemacht werden können.
Auch die Loggia wurde so weit wie möglich fertig gemacht. Zum ersten Mal konnten wir auf dem Balkon mit Geländer stehen.
11th November 18.00 clock
Today we were only in the evening on the site. The men of the company Scheddin were also fully occupied. Unfortunately, it turned out that our drawings (which were also applied for planning permission) and the detailed drawing for the craftsmen were different. There was thus a problem in the bathroom. The pretext behind the bathtub was made as a closed wall, although we did have a shelf level with the top edge of the tub, as mentioned in the drawings.
The wall of the basin was made today ready. The sanitary Müller was again on site and also have the electrical work fertig gemacht (um eine Fahrt der Elektriker von Berlin nach Langenbruck zu sparen).
Wir wollten eine horizontale 120 cm lange Vertiefung in der 140 cm langen Wand haben, was aber aus Statiksicht nicht möglich war, da dann einige vertikalen Querhölzern unterbrochen werden müssten.
Morgen wollen die Tischler fertig werden, aus dem Grund sind sie ziemlich im Stress; das Badezimmer muss noch fertiggestellt werden, die Loggia ist noch komplett offen und es fehlen noch einige Feinarbeiten. Mal sehen wie es morgen weiter geht...
09th November 19.00 clock
are today delivered the tiles. At the time where I was on site about one-third of the roof was covered with roof tiles. We need to look at the times in daylight, but I think that is very beautiful. The contrast with our lighter Fasadenfarbe is of course directly visible.
was also closed down on the ground floor the ceiling. The ceiling is clad entirely with Fermacell. Now we can start the spots to drill. Otherwise, the people are very busy with the roof.
morning visit during daylight and the whole thing looks like.
08th November 17.45 clock
Today, the company Scheddin back. If they are there mostly good stuff going forward, it is now going on with the detail work, as a precision tool with (!!!). the Kettingsäge This week, the wood work is finished.
was today made the bathrooms downstairs, and the installation of bathroom walls and side table have been completed. We still had some questions about the upstairs bathroom, all has been answered.
I also have used directly the question time to look to the questions whether Zimmerman's people have time and inclination to make the drywall in the kitchen, which was answered with a yes in principle. Even today we have the first style element in our TV wall cut. The box should be provided with a light. But had the power cables are redefined, then the wall cavity would be ready.
was made above the dormer finished. Now see how much space we gain in the two rooms at the front of our house, even with only 5.40 m wide dormer (instead 7m)
Erreichnis And most important of today and the cellar door is set. Finally we can sleep peacefully again. For weeks, some items were unsupervised in our open basement, now we can finally finish the basement. Also, we have directly the final key to our Get home. The lock cylinder needs to be replaced at the end of the work again.
Monday, November 1, 2010
Good Oxygenating Mouthwashes
construction Week 44 2010
This week was the assembly group is not there. The electrical and plumbing, however, some men have done.
The complete electric on the ground floor and was moved or prepared. Our outlet is in the dining room table looking even recognize (see Figure 5).
On Thursday evening and on weekends were then announced work on their own performance. On Thursday, a basement has been deleted. On the weekend then mounted the float in the rain water cistern and moved the cable to the basement. Then came the nurses and was the dormer and the 2nd Side of the wooden facade painted.
This week was the assembly group is not there. The electrical and plumbing, however, some men have done.
The complete electric on the ground floor and was moved or prepared. Our outlet is in the dining room table looking even recognize (see Figure 5).
On Thursday evening and on weekends were then announced work on their own performance. On Thursday, a basement has been deleted. On the weekend then mounted the float in the rain water cistern and moved the cable to the basement. Then came the nurses and was the dormer and the 2nd Side of the wooden facade painted.
Sunday, October 24, 2010
Black Blotvches On Lcd
construction Week 43 2010
30th October own performance Steichen exterior
Today we had to withdraw support to our external facade. The wood has a lot of structure, it has taken a long time. But the result speaks for itself. The color is almost the color of the window and is much more modern. We are curious how it will look with the roof tiles and bricks.
26th October 18.00 clock are already prepared some installations.
particular has done much in the attic. The Velux Venster was set;
The first insulation was laid in the ground, and fastened planking.
28th October 17.00 clock
one days on the job site was not directly equal a few increments means not noticed. It's crazy how quickly are changes. Today, all sides are level on the top floor and already is some proof.
The electrician from ELKU have given gas, the complete wiring is pulled across the house and installed as far as possible. It still lacks the earthed sockets and switches, because of course we have again what you want outside the standard range.
25th October 08.00 clock electrical, plumbing and installation work
Today was the first time really something going on the site. A total of eight people were busy building our house. Were
At 8.00 clock in the morning the chief engineer, the plumbing company and we Müller on the site. After we have spoken have carried the theme, the project supervisor was adopted and the Frank Miller got down to work. Today we started with the piping in the basement and in the guest bathroom.
After we had just finished talks with the supervisor and the plumbing, an order for electric cars were driven up to deliver installation. Less than 2 minutes later were also of the electricians ELKU from Berlin at the door. Even with whom we have spoken the issues. When I came back in the evening at the construction site a lot has happened. Were everywhere down the cables were holes drilled in the walls for electrical installations and pipes were laid in shower room and cellar.
30th October own performance Steichen exterior
Today we had to withdraw support to our external facade. The wood has a lot of structure, it has taken a long time. But the result speaks for itself. The color is almost the color of the window and is much more modern. We are curious how it will look with the roof tiles and bricks.
26th October 18.00 clock are already prepared some installations.
|
has also changed outside stuff. The dormer was insulated and made the pages. At the front pages was the Zierbeplankung attached and suspended the suspension of the rain gutter:
|
one days on the job site was not directly equal a few increments means not noticed. It's crazy how quickly are changes. Today, all sides are level on the top floor and already is some proof.
The electrician from ELKU have given gas, the complete wiring is pulled across the house and installed as far as possible. It still lacks the earthed sockets and switches, because of course we have again what you want outside the standard range.
25th October 08.00 clock electrical, plumbing and installation work
Today was the first time really something going on the site. A total of eight people were busy building our house. Were
At 8.00 clock in the morning the chief engineer, the plumbing company and we Müller on the site. After we have spoken have carried the theme, the project supervisor was adopted and the Frank Miller got down to work. Today we started with the piping in the basement and in the guest bathroom.
After we had just finished talks with the supervisor and the plumbing, an order for electric cars were driven up to deliver installation. Less than 2 minutes later were also of the electricians ELKU from Berlin at the door. Even with whom we have spoken the issues. When I came back in the evening at the construction site a lot has happened. Were everywhere down the cables were holes drilled in the walls for electrical installations and pipes were laid in shower room and cellar.
Monday, October 18, 2010
Blue Print For A Rale Gun
construction Week 42 2010
22nd October 18.00 clock
course, the differences of a geek are not as serious as the last days. The roof panel has been installed and, above all, House has done good stuff. Since Monday, the electrician has to come a lot to be prepared for what happened in the last 2 days.
20th October 09.00 clock
After a bad night's sleep (heavy rain event in Munich), it seems Langenbruck, in the opinion of local people "the most beautiful spots in Bavaria," to have been much smoother. From the heavy rain no language!
Today managed to have the porch and the dormer set and the roof is water tight in the evening, which is a pretty good feeling.
19th October 07.00 clock arrival in the construction area.
After a lot of "morning stress," we are just in time to see the building site to ensure that the first wall is lifted into the air. The ground floor is built up so quickly that concerns us, the thought crossed his mind that the roof within half a day on it is. After a short break for breakfast around 10 clock The ground floor is completely set.
the afternoon progresses, the construction progress more slowly, now it is little more "house", most parts must now be cut to proper size and can be measured and positioned correctly. In the evening, the highest point is reached. Unfortunately, the roof is not too.
22nd October 18.00 clock
course, the differences of a geek are not as serious as the last days. The roof panel has been installed and, above all, House has done good stuff. Since Monday, the electrician has to come a lot to be prepared for what happened in the last 2 days.
20th October 09.00 clock
After a bad night's sleep (heavy rain event in Munich), it seems Langenbruck, in the opinion of local people "the most beautiful spots in Bavaria," to have been much smoother. From the heavy rain no language!
Today managed to have the porch and the dormer set and the roof is water tight in the evening, which is a pretty good feeling.
19th October 07.00 clock arrival in the construction area.
After a lot of "morning stress," we are just in time to see the building site to ensure that the first wall is lifted into the air. The ground floor is built up so quickly that concerns us, the thought crossed his mind that the roof within half a day on it is. After a short break for breakfast around 10 clock The ground floor is completely set.
the afternoon progresses, the construction progress more slowly, now it is little more "house", most parts must now be cut to proper size and can be measured and positioned correctly. In the evening, the highest point is reached. Unfortunately, the roof is not too.
Thursday, October 14, 2010
How Much Is A Replacement Uk Driving License?
electric and telephone
After a long time nothing went on the property today is a major hurdle overcome, the electrical system of the DEA and the telephone connection of the Telekom are connected.
seemed, after many conversations with several contacts of EON, the scheduling Situation problematisch. Aber Ausdauer gewinnt, und statt 6 Wochen Vorlaufzeit war es nach 2 Wochen Wartezeit so weit;
Ohne Probleme wurde die Leitungen gelegt und vor allem wurde von den Herren mit gedacht wie wir mit weniger Leitungslängen auskommen würden; statt 38 m haben wir nur 14 m Leitung gebraucht, was einiges in den Kosten ausmacht.
After a long time nothing went on the property today is a major hurdle overcome, the electrical system of the DEA and the telephone connection of the Telekom are connected.
seemed, after many conversations with several contacts of EON, the scheduling Situation problematisch. Aber Ausdauer gewinnt, und statt 6 Wochen Vorlaufzeit war es nach 2 Wochen Wartezeit so weit;
Ohne Probleme wurde die Leitungen gelegt und vor allem wurde von den Herren mit gedacht wie wir mit weniger Leitungslängen auskommen würden; statt 38 m haben wir nur 14 m Leitung gebraucht, was einiges in den Kosten ausmacht.
Sunday, October 10, 2010
What Is The Difference Between Excpt And Cpht
Raceday, the report
Das sind die wichtigsten Dinge nach jedem T1 Wechsel aufs Rad, nicht nur hier in Hawaii. Basierend auf den Erfahrungen der vergangenen beiden Starts konntrollierte ich den Raddruck intensiv und dosierte nur vorsichtig die Kraft. Laut Marschplan abgeleitet aus meinen Trainingsaufzeichnungen sollten 220 Watt von Anfang bis Ende durchgetreten werden, 10 bzw. 20 Watt mehr im Schnitt als in den vergangenen Jahren auf gleicher Strecke.
The descent was as expected, extremely sensitive. My theory from the old sailor days following, in which the incident pointed to the sail (wheel) acting wind speed increases and thus causes fewer side drift, I made myself as small issue in full aero position on the bike and raced with Höstgeschwindigkeit down the mountain and mass of riders over, the fighting in the upper arm posture visibly nervous with the side winds. My wind shift was significantly lower than that of the supporters and my bike was like a board, so I made up many places.
Back on the Queen K 'Highway arrived, I had enough grain to maintain the planned pace. And as expected, I was the one who could pass to the other. My ERGOMO was finally 221 W average power (225W NP) and I knew that I do not rip quilting adventure and should have saved up enough energy for running. As I was during the bike ride again and again with new intervals and HF, TF, Watt and Average Watts values \u200b\u200bthe stopped working, had occurred to me only in the transition zone, the bike course had ended with a bomb time for me.
4:30 clock, 5:00 clock exit to the pier, Bodymarking, inflate tires, swimming suit (thanks Marco for the loan), it's Last photos the family and into the water!
As simple as the story writes the start of a race day, which takes place in Hawaii as in almost any other IRONMAN. Here is special, the mood of each individual with the knowledge that not to be beat for almost all participants of this event is. What is happening in our sport for over the Ironman World Championship in Hawaii?
So ist es auch besonders, wenn man sich langsam an die Startlinie heranschwimmt, die jetzt nur noch vereinzelt auftretenden Fische ins Auge fasst und einen Blick nach der einen oder anderen Unterwasserkamera riskiert. Wer jetzt noch keine Gänsehaut hatte wurde spätenstens beim Beginn der gesungenen Hymne von Hawaii schwach.
Die Stimmung wechselte von einer Sekunde zur anderen mit dem Startschuss. Hier weiß jeder, der schon einmal in Kailua-Kona gestartet ist, dass das, was folgt, den absoluten Ausnahmezustand wiedergibt. Ist man sonst gewohnt, sich nach kurzer Zeit freizuschwimmen, hängt man hier bis zum Schwimmausstieg im "Pack" und bekriegt sich gegenseitig bei der Wahl der besten Schwimmlinie. Und gut schwimmen können hier die meisten!
Ich hatte ím Gegensatz zu den vergangenen Jahren humane Mitstreiter um mich, d.h. das Gerangel hielt sich in Grenzen und ich konnte weitgehend meine Linie unter Ausnutzung meiner Möglichkeiten schwimmen. Oft suchte und fand ich "schnelle Füße" von einem vor mir schwimmenden Teilnehmer, um Kraft zu sparen.
Schon in der letzten Woche verlief mein Schwimmtraining verheißungsvoll. So war ich richtig happy, als ich nach ca. 1:07 Std. aus dem Wasser kam, glatte 3 Minuten schneller als meine Bestzeit auf dieser Strecke. Ich touchierte zuletzt noch the feet of Danny, who swam at the exit in front of me, but I could not make themselves understood to have her good wishes to give up the path.
Bike record bag, swimming suit off and put on T-Shirt, the wheel running, helmet on, glasses on and barefoot - the cycling shoes I always fix the wheel - with the hands start moving the wheel.
It all happened very fast, but wg. the Umzieherei, especially in the longsleeve compression shirt, the change in me takes a little longer. This delay, I am happy to accept it, I'd been burned often enough in such a scorching sun, dass ich Tage danach noch mit den Auswirkungen zu kämpfen hatte.
It all happened very fast, but wg. the Umzieherei, especially in the longsleeve compression shirt, the change in me takes a little longer. This delay, I am happy to accept it, I'd been burned often enough in such a scorching sun, dass ich Tage danach noch mit den Auswirkungen zu kämpfen hatte.
Sofort die erste Iso Flasche austrinken, Gel einwerfen, Tempo kontrollieren!
Das sind die wichtigsten Dinge nach jedem T1 Wechsel aufs Rad, nicht nur hier in Hawaii. Basierend auf den Erfahrungen der vergangenen beiden Starts konntrollierte ich den Raddruck intensiv und dosierte nur vorsichtig die Kraft. Laut Marschplan abgeleitet aus meinen Trainingsaufzeichnungen sollten 220 Watt von Anfang bis Ende durchgetreten werden, 10 bzw. 20 Watt mehr im Schnitt als in den vergangenen Jahren auf gleicher Strecke.
Erwartungsgemäß überholten mich anfangs reichlich Triathleten, was mich aber nicht beunruhigte, hat mein ERGOMO Wattleistungsmesser doch immer zuverlässig die Daten geliefert. Bis nach Kawaihae konnte ich die Kraft im erwarteten Bereich gut dosierern, danach folgt ein längeres Stück bergauf und mit Gegenwind nach Hawi. Von hier standen 230-240W auf dem Plan, wissend, dass das Stück zurück durch Gefälle und Rückenwind geprägt sein würde und die getretene Leistung daher geringer ausfällt. So war es dann auch: Starke Windböen fielen erst von der Seite, dann von vorne über uns her und es gab einige gefährliche Situationen, in which cyclists were threatening to plunge and at least three seriously crashed on the descent, as we learned later.
The descent was as expected, extremely sensitive. My theory from the old sailor days following, in which the incident pointed to the sail (wheel) acting wind speed increases and thus causes fewer side drift, I made myself as small issue in full aero position on the bike and raced with Höstgeschwindigkeit down the mountain and mass of riders over, the fighting in the upper arm posture visibly nervous with the side winds. My wind shift was significantly lower than that of the supporters and my bike was like a board, so I made up many places.
Back on the Queen K 'Highway arrived, I had enough grain to maintain the planned pace. And as expected, I was the one who could pass to the other. My ERGOMO was finally 221 W average power (225W NP) and I knew that I do not rip quilting adventure and should have saved up enough energy for running. As I was during the bike ride again and again with new intervals and HF, TF, Watt and Average Watts values \u200b\u200bthe stopped working, had occurred to me only in the transition zone, the bike course had ended with a bomb time for me.
jumping barefoot from the wheel, recording the run-bags and into the changing tent, socks and running shoes, Fuel Fold Belt with the prepared Gel-/Salzflaschen and hit the run course!
The run proved to be a little difficult at the beginning. Although I was traveling quickly, but I was not such a great feeling. So I had until after a stop at KM 8 Dixi wait until the legs felt quite well. Get round it felt until I had the slope of the Palani Road behind me and I opened myself in the lava desert to the Energy Lab. Half way I turned to this Very first time my best tactic, "Go in the catering areas to carefully ice-water and food intake and immediate restart after completion of the necessary". As the pace for the distance between the stations I chose 4:45 min / km, which should aim at a 3:30 hour marathon.
During the marathon I kept coming to mind, the "total system Dirk" to check and found time and again that everything was alright. Although the soles of the feet to KM 35 felt already plenty painful, but such occurrences are preparing not really worried at the prospect of the approaching end of competition.
During the marathon I kept coming to mind, the "total system Dirk" to check and found time and again that everything was alright. Although the soles of the feet to KM 35 felt already plenty painful, but such occurrences are preparing not really worried at the prospect of the approaching end of competition.
Just before turning into the Palani Road encountered a German-language triathlete, that the end probably just over 10 hours would be, and for me at that time on this route is not considered possible value. Although my lap times could have been used to bring the knowledge, but my calculation skills were, I already knew of me, progressively with increasing duration of the race. The "home run" on the Alii Drive proved to be difficult again because I was out of sheer euphoria probably increased the pace of the last 1,000 m too much. Less than 300 meters from the finish line reported to the calves and failed to alert the United Cramps almost their service. I again took out some speed and concentrated on good and upright to cross the finish line.
... 75 meters ... |
The joy was great!
... done! |
Summary
- Total time: 10:02:53 hrs
- Swimming 1:07 47
- cycling: ; 5:19:13
- run: 3:29:12 run,
- place 482 in the overall standings,
- place 32 age group.
I have achieved all the objectives for Hawaii 2010, also the one I had not made up my mind. In advance I would have a place among the top 500 can not imagine. All sections, starting with swimming, cycling and running each beat my most optimistic expectations. I can only explain with an absolutely perfect day, a happy and successful training and Taperphase with the optimal pacing and nutrition plan. Hopefully works in the future, a similar race in which I think in retrospect no improvement could.
And so I look forward to a future with more races and similarly beautiful feelings of happiness.
Wednesday, October 6, 2010
Why Does Tip Of Big Toe Hurt
Hawaii Splitter ... Continued
as the first week in Hawaii under the auspices of the final Akklimation and training, are in the week of competition for us hardcore chill shopping more, and study the latest triathlete needs in the program.
Ford Ironman fair opened on Tuesday with the state entry Parade of Nations and opened its doors - not admittedly quite expensive land of plenty - for kaufwütige triathletes.
Click here for everything away like hot cakes, what is imprinted with "Ironman 2010". Wrist watches, sports and leisure clothing, backpacks, stickers, coffee mugs and memorabilia related to dog collar, leash and fressnapf here who buy them.
latter was presented at the same Digm-Beach.
The Digmebeach like slow a madhouse. For the last week, yet leisurely start mile is a mass arrival with hectic bustle from 6:00 Clock to 10:00 clock become. Here it is obviously to show colleagues how great it is measured by its own ordered on fitness or physique is necessary to have instilled respect.
Fortunately, I know that muscle bulk are usually no big runner and I will be manageable with my muscle mass, at least on the running track a slight advantage.
Fortunately, I know that muscle bulk are usually no big runner and I will be manageable with my muscle mass, at least on the running track a slight advantage.
In the meantime, we have found with other students symbiotic well. The little house gecko we have already noted on feeder. The fact that this little creature but at the pleasure of caffeine stains the floor of the porch was, we discovered only today. With pleasure, he sipped from the bottom of the drops generated during the pouring of the cups. Of course, we have burned to the to the SD card. determined